AT&T Construction Through August

AT&T will be installing a number of infrastructure improvements for its wired communication services, including placing Lightspeed cabinet boxes in Redwood Shores for U-verse high-speed internet, television and telephone service. Because of this, construction crews will be at various sites throughout the month. Please be on the lookout in these areas to slow down while passing construction zones stay extra wary of pedestrians when passing these sites.

The proposed construction schedule for Redwood Shores is as follows:

Batch 1:
Estimated window start time: Week of 7/25/2011

  • Davit and Shell
  • MH 755 Redwood Shores PKWY
  • 1 Egret Ln

Batch 2:
Estimated window start time: Week of 8/8/2011

  • 601 & 650 Redwood Shores PKWY
  • 1 Avocet Dr
  • 440 Marine PKWY

Batch 3:
Estimated window start time: Week of 8/22/2011

  • 455 Compass Cir
  • 397 Lanyard Dr
  • 800 Marine PKWY
  • 595 Shell PKWY

Batch 4:
Estimated window start time: Week of 9/5/2011

  • 400 Tiller Ln
  • 554 Marine PKWY
  • 700 Marine PKWY
  • Shearwater & Mindanao