Dredging Update for March 2010

Many of you have seen the dredging taking place in the main lagoon areas — Redwood City thanks you all for your ongoing patience! Unfortunately, the contractor has come across a significant amount of debris in the lagoon, such as old rebar (metal), pieces of concrete, and hundreds of golf balls, This required him to stop work to remove this debris, which has slowed down the operation. Dredging in the main lagoon area (primarily around Shorebird Island) is now expected to be completed by the end of April.

A second phase of dredging is scheduled to start by early April, in the lagoon between Sandpiper Lagoon Subdivision No. 1 and Bridgeport Subdivision. Work will take place on weekdays only, through the end of April, and the machinery in the lagoon will operate between 8 am and 4:30 pm. Sediment will be loaded into trucks (not every day; only when sufficient amounts have been stockpiled for removal) and hauled out for re-use or disposal. To accomplish this, the outer eastbound lane of Redwood Shores Parkway will be closed to traffic for a segment between Avocet Drive to Egret Lane between 9 am and 2:30 pm daily; access to Waterside Circle and Bay Harbour Drive will be maintained.

Dredging Update for February 2010

This update is to let you know that the project will not be completed by the originally-expected date of January 31, 2010. Unfortunately, the contractor is uncovering some unforeseen conditions that have slowed the work progress. As they’ve been working, the contractor has discovered old rebar (metal), pieces of concrete, and even hundreds of golf balls in the lagoon. Because the contractor has to stop work and remove this debris, this has slowed down their operation.

The City has received approval from the U.S. Army Corps of Engineers and the Regional Water Quality Control Board to continue the work past the original end date, subject to certain restrictions (avoiding “ground disturbing activities”). Assuming that the contractor does not run into any further significant unforeseen debris in the lagoons, they anticipate the work to be completed by the end of February, 2010. This work will be focused on the lagoon around Shorebird Island (dredging zones 3, 4, and 5).

Please visit www.redwoodcity.org/shoresdredging for information about this project, or to be added to the email list.

For immediate concerns with ongoing work, contact the contractor, Lance Dohman, at 650-868-8240. For questions about the overall project, please call Brian Lee, Redwood City Supervisory Civil Engineer, at 650-780-7391.

Again, thank you for your understanding as we continue with the dredging project, which will result in a cleaner, more appealing lagoon in Redwood Shores.

Dredging On Saturday

Just a note to let you know that the City has given the dredging contractor permission to work Saturdays from 8 am — 4 pm throughout January. It turns out that this adjustment is necessary in order maintain the schedule for completion. Additionally, the contractor is utilizing up to two additional “aquamog” pump barges to accelerate the work.

Dredging Update

The dredging will continue until December 18 – dredging will begin in the lagoon closest to Area H, north of Marine Parkway only (Zone 9A)

*Over the next two weeks, the contractor will be installing the floating pipeline that will be used to pump dredge material later from the lagoons around Shorebird Island (Zones 3,4,5) to Area H.

*By mid-December, the contractor will place a booster pump on a small barge, in the main lagoon approximately halfway between Shorebird Island and Area H.

*During the last week of December, and continuing through mid-January, the contractor will be dredging the lagoons around Shorebird Island.

*During January the contractor will complete remaining areas – portions of the lagoon near Area H, but south of Marine Parkway (Zones 8 and 9).

*By January 31, the contractor should be complete, and cleanup/demobilization of equipment will take place.

And as a reminder, the work hours will be 7:30 am – 4:00 pm, weekdays only. Boaters need to be very aware of the floating pipeline, which will be well-marked. While it’s in place, it will not be possible for boats to cross over the pipeline, as it will be only partially submerged. This may be a particular issue for residents living on parts of Shorebird Island, and along the northern side of the main lagoon, during the period while the Shorebird Island area is being dredged. Once Shorebird Island lagoon is dredged, the pipeline will be removed and boats will have access. The contractor will have floating buoys and markers attached to the pipeline to clearly indicate its location.

Lagoon Dredging Update

In October, the City Council approved a contract with the firm Aquatic Environments to perform dredging in certain lagoons at Redwood Shores. This work will help specified areas of the lagoon to better “flush” and therefore improve water quality and appearance (please see www.redwoodcity.org/shoresdredging ).

As part of the outreach to affected residents, in addition to a direct mail flyer and an article in last month’s Pilot, the Redwood Shores Community Association and Redwood City hosted a project community information meeting on Thursday, October 22, 2009, during which residents heard from and asked questions of City staff, contractors, and consultants. At that meeting, staff provided an overview of the project, outlined the scope of work, and presented a tentative schedule. Here is a brief overview:

* The two areas to be dredged are the lagoon around Shorebird Island, and portions of the lagoon near Area H between Laguna Pointe and California Harbor Court.
* It’s expected that the contractor will begin prep work the first week of November, and start actual dredging a bit later in the month (a more specific schedule will be available on the project website in November).
* The work hours will be 7:30 am – 4:00 pm, weekdays only.
* While the contractor has up to 180 days to complete the work, it’s expected that the dredging will be completed by January 31st.
* Dredging will be done with one or two small barges which will hydraulically pump the sediment from the lagoon floor, sending it through a pipeline running along the main lagoon, to be deposited into Area H as part of the wetland restoration.

The key issues raised by residents attending the meeting, and summaries of staff responses, were:

* The expected noise levels of the dredge machinery and booster pump.
Some level of noise is unavoidable, but it is temporary. The contractor estimates that the noise of the pumps is similar to a mid-sized pickup truck engine. The expected noise level is approximately 80-85 decibels at 20 feet distance from the machinery. The machinery utilizes mufflers and is enclosed to minimize noise. We ask for residents’ patience throughout this project.

* Inability to launch boats from certain areas while the temporary pipeline is in place.
While it’s in place, it will not be possible for boats to cross over the pipeline, as it will be only partially submerged. This may be a particular issue for residents living on parts of Shorebird Island, and along the northern side of the main lagoon, for about a month while the Shorebird Island area is being dredged. Once Shorebird Island lagoon is dredged, the pipeline will be removed and boats will have easy access. The contractor will have floating buoys and markers attached to the pipeline to clearly indicate its location.

* There will only be partial dredging in the lagoon between Laguna Pointe and California Harbor Court.
Some parts of this lagoon contain the compound PAH (polycyclic aromatic hydrocarbons – likely from roadway runoff) in levels higher than is allowed for use as wetland restoration fill. Such sediment would have to be mechanically dredged and trucked to an alternate disposal site, at a significantly higher expense than disposal in Area H. Because of this higher expense, it is not financially feasible at this time for the City to dredge those portions of this lagoon – therefore only specified sections of this lagoon will be dredged. The City’s intent is to determine a way to finance the complete dredging of this area at a later date, once funds are fully available, likely several years away.

Much more information and diagrams are online at the City’s project website at www.redwoodcity.org/shoresdredging. There, you can also sign up to receive periodic updates via email.

The City and its contractor wish to thank the Redwood Shores community for its patience and understanding as this lagoon dredging project gets underway – the result will be an improved lagoon that more positively contributes to the beauty and pride of Redwood Shores, as well as the quality of life of its residents.